John Beever Australia
16 November 2015
DDS Australia have provided John Beever with support to numerous projects, our on going relationship is testament to the performance and delivery we have provided time after time.
Our primary role is to produce resourced plans comprising of the full WBS, activity sequencing and manhour histograms for tender programs, live projects and also to build the knowledge and processes within their organisation.
November 2015 - April 2016
Origin Energy HBWS SMP Project, Port Campbell:
- Develop schedule in Primavera
- Resource Level schedule and produce histograms
- Site planning to convert the construction schedule into a manageable startup / commissioning schedule
September 2015
Baryulah LLP Compression Project:
- Produce resourced schedule
- Provide sequencing and estimated durations based on working drawings
September 2015
SPC Tomato Plant Utilities:
- Develop schedule to fit into client master program
- Produce manhour reports
August 2015 - December 2015
Origin Energy OGP Civil Works Program:
- Develop fully resourced schedule
- Assistance in EOT claims and analysis of baseline schedule
- Progressing schedule, liaison with on site project team
- Producing S Curves and manhour / cost reports
June 2015
Port Pirie Transformation Project:
- Produced detailed tender schedule in Primavera
- Resource schedule based on estimates
- Review construction drawings for activity and work sequencing
- Produce histograms
February 2015
Project Bunge (Silo and Civil works program):
- Develop project schedule
- Resource level
- Produce manpower histograms
January 2015
Grain Corp (Project Regeneration):
- Produce schedule
December 2014
Cargill Grain Project (Project Pearl):
- Produce detailed Tender program in Primavera
- Liaise with project team to develop constructability
- Work with chief estimator to ensure durations and manhours were detailed and correct
- Produce histograms